Hi @LNTU-YS, I think setting sampling to 1 (= 1 day in MJD) should solve this problem. This will loop from January 1st up to and including January 31st. Cheers, |
Beta Was this translation helpful? Give feedback.
1 reply
-
Hi @LNTU-YS, thanks for the clarification. LoopTime will not help you in that case, as it will process each day individually (i.e. just execute the program for each day). Without the .xml file, I can only guess but two things to check are:
Let me know if that helps, |
Beta Was this translation helpful? Give feedback.
1 reply
Sign up for free
to join this conversation on GitHub.
Already have an account?
Sign in to comment
-
Hello,
I have encountered a problem like this. When I use “SlrParametrization ”and “StaticPositions”, I use one day's data to obtain station coordinates. What should I do if I want to use multiple days' data to determine station coordinates now? I tried the time loop and found that only the data from the first day is used each time. My settings are shown in the following figure:
I have also tried “TimeSeries -Monthly ”and “TimeSeries -EveryMonth ”, but found that they cannot achieve the results I want. I don't know where the problem lies, I hope you can give me some ideas.
With Kind Regards
YUAN
Beta Was this translation helpful? Give feedback.
All reactions